Penticton Foundry Milestones
on July 23, 2012In a continuing effort to maintain and improve upon our foundry process, Penticton Foundry has made many changes over the years.
2011/2012
- Built an additional core room
- Installed a new box shaker
- Developed and produced new products (Clamshell Assemblies)
- Installed a backup power generator for the melt deck
- Upgraded/extended cranes for pouring floor
- Increased crane tonnage for floor moulding area
- Upgraded white iron grinding cells
2010/2011
- Purchased a new mixer for the AMC (Automated Moulding Center)
- Installed a new roof on the primary foundry building
2009/2010
- Extended the 10T crane on the pouring floor
- Plant I
- Purchased the neighboring building
- Installed a new roof on the building
- Installed new 5T cranes
2007/2008
- New AJAX power pack, for the melt deck
- New transformer & housing unit for AJAX
2006/2007
- Added an additional 10T crane to the pouring floor.
2005/2006
- Designed and built the new AMC (Automated Moulding Center)
2004/2005
- Purchased new 10T cranes for the pouring floor
- Purchased a new compressor
2003/2004
- Built an additional pattern storage building
2002/2003
- Purchased a new 1,000 Lb mixer
- Updated the pouring crane (5T)
2001/2002
- Purchased a core blower for the core room
- Purchased an excavator for the scrap yard
2000/2001
- Purchased a new spectrometer